深部巨厚煤层强采动下底板多功能巷道布置层位参数研究

Study on layout parameters of floor multifunctional roadway in deep ultra-thick coal seams under strong mining disturbance

  • 摘要: 深部巨厚煤层开采扰动剧烈,底板多功能巷道围岩大变形失稳问题突出,其根本原因在于对采动底板不同深度应力环境演化规律认识不清,导致层位选择缺乏理论依据与定量判据。以彬长矿区小庄煤矿为工程背景,综合采用理论分析、相似材料模拟、数值计算及现场实测验证等手段,对底板多功能巷道合理布置层位进行系统研究,提出了底板采动应力环境三区划分方法和层位优选判据。通过理论计算得出底板最大破坏深度为18.37 m,巷道应布置于20 m以深以规避采动直接损伤区。通过相似模拟试验揭示底板采动应力环境沿垂深呈现显著三区特征:小于30 m为强卸荷扰动区(I区),应力波动标准差达0.018 MPa,加卸载频次≥8次/周期;30~50 m为应力波动与集中区(II区),应力路径呈“加载−卸压−再加载”特征,存在应变突变风险;大于70 m为应力平稳过渡区(III区),应力波动幅度<0.01 MPa,扰动充分衰减。数值模拟结果表明:30 m层位呈非协调剧烈变形模式,顶底板移近量达1 068 mm;50 m层位呈底鼓主导的非对称变形模式,最大底鼓量为190.5 mm;70 m层位偏应力比显著降至1.5~1.8,围岩趋于整体协调抬升,最大底鼓量为159.5 mm,顶板隆起39.7 mm,净移近量仅为30 m层位的11.2%。建立了底板多功能巷道层位优选的4步决策逻辑:破坏带规避−应力分带优选−岩性条件校核−工程实证验证,得出最优层位为煤层底板下方70 m左右的稳定岩层。小庄煤矿南部底板多功能巷道现场监测数据表明,该层位巷道在采动全周期内顶底板移近量小于100 mm,顶板离层小于30 mm,围岩应力波动平缓,实现了长效稳定运行。

     

    Abstract: Deep ultra-thick coal seam mining causes severe disturbance, and the surrounding rock of floor multifunctional roadways exhibits significant deformation and instability. The fundamental reason is the unclear evolution of the stress environment at different depths of the mining-disturbed floor, which leads to the lack of theoretical basis and quantitative criteria for roadway horizon selection. Taking Xiaozhuang Coal Mine in the Binchang mining area as the engineering background, this study systematically investigated the reasonable layout horizon of floor multifunctional roadways using theoretical analysis, similar material simulation, numerical simulation, and field measurement verification. A three-zone classification method for the mining-induced stress environment of the floor and a horizon optimization criterion were proposed. Theoretical calculations showed that the maximum failure depth of the floor was 18.37 m, indicating that the roadway should be arranged at a depth greater than 20 m to avoid the direct mining-damaged zone. Similar simulation tests revealed three distinct zones along the vertical depth of the floor mining-induced stress environment: the strong unloading disturbance zone (<30 m), characterized by a stress fluctuation standard deviation of 0.018 MPa and loading–unloading frequency of ≥8 times per cycle; the stress fluctuation and concentration zone (30–50 m), characterized by a "loading–unloading–reloading" stress path and potential strain mutation risk; and the stable stress transition zone (>70 m), where stress fluctuations were less than 0.01 MPa and disturbances were sufficiently attenuated. Numerical simulation results demonstrated that the roadway at the 30 m horizon exhibited severe incompatible deformation, with the roof-to-floor convergence reaching 1 068 mm; the roadway at the 50 m horizon showed asymmetric deformation dominated by floor heave, with a maximum floor heave of 190.5 mm; and the roadway at the 70 m horizon exhibited coordinated overall uplift, with the deviatoric stress ratio reduced to 1.5–1.8, a maximum floor heave of 159.5 mm, roof uplift of 39.7 mm, and net convergence only 11.2% of that at the 30 m horizon. A four-step decision-making logic for horizon optimization of floor multifunctional roadways was established: failure zone avoidance–stress zoning optimization–lithological condition verification–engineering validation. The optimal horizon was determined to be the stable rock layer approximately 70 m below the coal seam floor. Field monitoring data from the southern floor multifunctional roadway of Xiaozhuang Coal Mine showed that the roof-to-floor convergence was less than 100 mm during the entire mining cycle, roof separation was less than 30 mm, fluctuations in the surrounding rock stress were mild, indicating that the roadway achieved long-term stable operation.

     

/

返回文章
返回